MB6-885 Dumps

Wednesday 4 July 2018

Free Download Microsoft MB5-705 Exam Dumps Questions

Question NO : 8

During your requirements and process review, you use the questionnaires provided by Sure Step. What is one of the reasons that you use the questionnaire at this stage?

A. to assist in determining the budget of the project
B. to use as a tool by the partner prior to meeting with the customer
C. to create detailed process maps
D. to use as a checklist and a reminder of topics to investigate

Answer: D

Explanation:

 http://technet.microsoft.com/en-us/library/aa569899.aspx A questionnaire is a set of questions that is used to collect information for variety of purposes. You can design, create, distribute, and complete questionnaires, and then analyze the results. You can customize a questionnaire to fit your specific needs by using a combination of the various features that are available in Microsoft Dynamics AX. For example, questionnaires can be used to: Test the professional skills of employees and applicants.
Test course participants at the end of the course. Evaluate a course, including facilities, content, and instructor. Survey employee and customer satisfaction. Evaluate employee job performance. The following table provides links to informat

Microsoft MB5-705 Exam Dumps Questions & Verified Answer Dumps4Download

Monday 4 June 2018

Prepare MB5-705 Question Answers - MB5-705 Exam Dumps - Dumps4Download.

Question NO : 7

Which two components are critical to the success of user acceptance testing? (Each correct answer presents part of the solution. Choose two.)

A. the completion of the end user training
B. the building of the disaster recovery environment
C. the usage of user acceptance test scripts
D. the transactions to use for the tests

Answer: A,C

Explanation:

A: The standard Sure Step process defines that end user training is required prior to user acceptance testing. C: Together with the key users, we can now prepare the user acceptance test scripts that will guide the UAT (user acceptance testing) during the Deployment phase.

Note:


Monday 16 April 2018

Get Latest MB5-705 Dumps Questions - 2018 MB5-705 Dumps

Question No : 6

You are delivering a project by using the waterfall delivery method.You approve the project charter and project plan.Which three actions should you do next? (Each correct answer presents part of the
solution. Choose three.)

A. Document the configuration of the overall Microsoft Dynamics solution.
B. Create the deployment plan.
C. Perform and document the Fit Gap Analysis.
D. Complete the design specifications.
E. Develop future state business process models.
F. Conduct the Executive and Project Team kickoff meetings.

Answer: C,E,F

Thursday 15 March 2018

Microsoft Free MB5-705 Exam Dumps4downlod.in

Question No : 1

You need to create a project by using the Sure Step Project Creation Wizard.Which two properties must you identify in order to proceed? (Each correct answer presents part of the solution. Choose two.)

A. engagement type
B. product
C. project implementation phase
D. product version

Answer: A,B

Question No : 2

You are responsible for creating and managing projects in a project repository. Which two actions can you perform on existing projects in the repository? (Each correct answer presents part of the solution- Choose two.)

A. clone a project
B. share a project
C. change a project type
D. delete a project

Answer: A,D


2018 Valid Microsoft MB5-705Dumps Questions - Microsoft MB5-705Braindumps Real Exam Dumps

Question No : 3

You are conducting the transition from solution to support. Which project phase are you in?


A. quality management
B. project close
C. deployment
D. operations

Answer: D

Question No : 4

You are a project manager. You use the classic triple constraint model. If one constraint is changed, what happens to the other constraints?

A. The project's quality constraint will change.
B. The project's expectations constraint will change.
C. At least one of the other constraints must also change.
D. The customer's benefits constraint will change.

Answer: C

Microsoft MB5-705Exam Dumps PDF Questions - MB5-705 Best Study Material

Question No : 5

Which activity may be included in project closure?

A. Provide additional user training.
B. Establish ongoing quality and testing strategy.
C. Conduct a disaster recovery test.
D. Review the scope and change requests.

Answer: A


Exact Microsoft MB5-705 Exam Real Questions - Microsoft MB5-705 100% Passing Guarantee